Original research analysis

Shaanxi Youth-Football Centre: Refurbishment Design Contract

The 2026 notice and its attachment describe a CNY 246,000 agreement for design services, requiring eight sets of construction drawings, with payments tied to signing, drawing review and completion acceptance. These are contractual terms; actual payment and acceptance remain unestablished.

Record date (source acquisition dates below) Oct 2, 2026 · Original editorial and source-scope review

Parties and design scope

Shaanxi Provincial Sports Training Centre is the buyer; China Northwest Architecture Design and Research Institute Co., Ltd. is the design provider. The agreement covers refurbishment of the provincial youth-football centre’s indoor field, with construction drawings selected in the stage table.

1 section citations

Deliverables and design support

Eight complete drawing sets are due within 10 days of scheme confirmation. The document does not specify working days. No fixed due date or actual delivery is established; no calendar deadline is calculated.

The agreement also requires review support, within-scope adjustments and site technical handover. Personnel are to attend within 48 hours of buyer notice, or 24 hours in an emergency. This does not establish actual attendance.

1 section citations

Conditional payment milestones

First: 30%, or CNY 73,800, within 7 days after signing.

Second: 50%, or CNY 123,000, within 7 days after all drawings are submitted and pass review by the buyer/drawing-review body.

Third: 20%, or CNY 49,200, within 7 days after successful project-completion acceptance. Valid invoices are required; issuing an invoice does not prove receipt of funds. No instalment is established as paid.

1 section citations

Dates and the two identifiers

The cover states 31 July 2026, matching the notice’s reported signing date. Published on 3 August 2026, the notice lists a 31 July–31 December 2026 performance period. Its end date does not establish completion or acceptance.

The notice identifier is HT-[provincial level]-2026-03349 (middle segment written in Chinese); the designer-entered cover identifier is 26-223. Both are retained separately.

1 section citations

Evidence and identity limits

Organizational seals and marks in signing areas are visible. Their authenticity and signing authority are not authenticated. The cover’s Grade-A architectural-industry wording has not been checked against an issuing register.

Effectiveness is conditional on signing/sealing and an advance payment. Without payment evidence, the effective date, paid amount, delivery date and acceptance date remain unknown.

1 section citations

Project facts & term boundaries

Procurement requirements and contract terms retain distinct sources. Budgets, ceilings, contract figures and actual payments remain separate. Performance and completion are unverified.

Buyer

Shaanxi Provincial Sports Training Center

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

Contract parties; main contract information; contract signing date; contract notice date

Design service provider

China Northwest Architectural Design and Research Institute Co., Ltd.

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

Contract parties; main contract information; contract signing date; contract notice date

title zh

Provincial youth football training centre: indoor venue repair and renovation design

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

Contract parties; main contract information; contract signing date; contract notice date

contract publication date

2026-08-03

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

Contract parties; main contract information; contract signing date; contract notice date

Attachment cover signature date

2026-07-31

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 1/2 cover

Notice-reported signature date

2026-07-31

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

parent official contract notice / original frozen case identity

signature date comparison

cover printed date agrees with notice date; signature page carries no separately observed date

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF covers and physical page 10 versus notice section VII

design stage

construction_drawing_design

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 4, printed page 2, Article 2 scope table

Source-stated contract design fee (CNY)

246000

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

deliverables · 0 · deliverable zh

Full construction drawings for the indoor venue repair and renovation project

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

deliverables · 0 · due trigger zh

After the scheme is confirmed

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

deliverables · 0 · due interval

10

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

deliverables · 0 · due unit

days

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

deliverables · 0 · calendar due date

unknown

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 0 · percent

30

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 0 · amount cny

73800

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 0 · trigger zh

After the contract is signed

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 0 · due interval

7

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 0 · due unit

days

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 1 · percent

50

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 1 · amount cny

123000

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 1 · trigger zh

After all construction drawings are submitted and pass review by the employer / drawing-review body

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 1 · due interval

7

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 1 · due unit

days

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 2 · percent

20

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 2 · amount cny

49200

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 2 · trigger zh

After the project passes completion acceptance

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 2 · due interval

7

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

payment schedule · 2 · due unit

days

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

PDF physical page 5, printed page 3, Articles 4–5

notice performance period preserved · start

2026-07-31

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

parent official contract notice / original frozen case identity

notice performance period preserved · end

2026-12-31

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

parent official contract notice / original frozen case identity

evidence boundary

Attachment terms and visible marks deepen the notice but do not establish payment, drawing delivery, review success or completed acceptance.

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

producer bounded review; absence is scoped to reviewed materials

actual payment amount cny

unknown

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

producer bounded review; absence is scoped to reviewed materials

actual design delivery date

unknown

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

producer bounded review; absence is scoped to reviewed materials

actual completion acceptance date

unknown

Source notice/attachment term. Payment triggers do not prove payment, delivery or completion. Blank attachment signature dates remain unknown; Tongchuan amount-in-words conflict remains unresolved.

producer bounded review; absence is scoped to reviewed materials